Mumbai: Central Railway completes 63-hour mega block 
Mumbai

Central Railway completes platform widening work at Thane after 63-hour mega block

Mumbai | The Central Railway on Sunday said it has completed widening work of platforms 5 and 6 at Thane.

The CR shared details about the special block for infrastructure upgrade work at Thane station. It said the platform 5/6 has been widened by 2-3 metres over a length of 587 metres.

The Central Railway had initiated a 63-hour mega block at Thane railway station and a 36-hour special block at the Chhatrapati Shivaji Maharaj Terminus. The mega block began at midnight on May 30-31 (Thursday-Friday night).

The platform widening project involved the use of 750 pre-cast hollow blocks and required the coordination of 400 workers, 20 teams and 10 contractors, a CR official said.

As many as 935 trains were cancelled during the 63-hour period, the official said.

ADGP's explanation to CMO on meeting with RSS leader draws flak in Kerala

Manipur: 5 killed in fresh violence in Jiribam; CM meets Guv to discuss law and order situation

Pakistan Army Chief acknowledges role of Pak army in Kargil war

Women in Cinema Collective to propose code of conduct in Malayalam film industry

Govt making efforts to recognise bright teachers adopting innovative methods: PM Modi